28 Sep 2020
Bridge – M80 E.J. Whitten Bridge – VIC
Key Highlights
Construction dates: August 2016 – September 2018
Construction value: $300 million
Project details:
- 5km of freeway widening,
- Seven freeway on/off ramps,
- Central widening of the existing E.J. Whitten Bridge.
Services supplied:
- Survey management and all survey resources including 1x structure surveyor and 3x road surveyors,
- Terrestrial laser scanning conducted on underside of existing E.J. Whitten Bridge, to ensure new structure was compatible,
- Set out of all civil works associated with a large-scale freeway infill and upgrade,
- As-built and reporting to Vic Roads specifications,
- Structural surveying services performed: set out of cross heads; bearing replacements and steel girta replacements associated with the infill of the existing E.J. Whitten Bridge.