M12 West Project

Key Highlights

Construction dates: October 2022 – December 2025

Construction value: $500 million

Client: CPB Contractors & Georgiou Group

Project details:

  • 6 km of new dual carriageway between the Northern Road, Luddenham, and 400 m east of Badgery’s Creek,
  • 11 bridges to be constructed, ensuring seamless passage over various obstacles such as waterways, roads, and railway lines,
  • Grade-separated interchange connected with the Western Sydney Airport,
  • Dual carriageway with lanes for both directions.
M12 West Project

Services supplied:

  • Supplied up to 12 experienced construction surveyors,
  • Installation and measurement of site-wide survey control network to TfNSW GC71 specifications,
  • Survey management of 11 bridges,
  • Earthwork, services, drainage, set-out and reporting,
  • Concrete and pavement set-out reporting with stringless paving machines.