3 Sep 2020
Road – Westconnex 2B, M5 and St Peters Interchange – NSW
Key Highlights
Construction Dates: 2016 – 2019
Construction Value: $5Bil
Client: Joint Venture – CPB Contractors & Dragados Samsung
Project Details:
- Nine kilometre twin motorway tunnels to accommodate up to 3 lanes of traffic in each,
- Surface road widening works along the M5 East Motorway,
- New road interchange at St Peters,
- New road bridge,
- Upgrade to local roads near St Peters Interchange and
- Motorway control centre.
Services Provided:
- Supplementary survey resources at St Peters Interchange, Kinsgrove Tunnel entrance and building construction at Bexley,
- Earthworks, bridge construction and building construction,
- Included up to 6 surveyors/teams.